Bi-Weekly As-Salam Mosque Project Update – September 14, 2023

Alhamdolillah, the construction work on the As-Salam Mosque Project commenced during the first week of September 2023. Praise be to Allah swt for bestowing us this joyous occasion.

The contractor has begun earth excavation. The next step is pile work, on which the Mosque floor will rest, which is going to commence in a few days. The Project Team has also recommended to the Board awarding a contract for civil works. This includes water, sewer and storm water lines and several other civil works components. Once approved the Civil Works contractor will also be on site very soon. The Project Team has also finalized recommendation for the elevator. While the elevator is one of the last items to be installed, the contractor must be chosen now to ensure design is prepared to meet elevator specifications.

On the building design side of things, IAOS has received the final building drawings. Mechanical, structural and electrical drawings are also expected in the next few days. IAOS will apply to the City of Regina soon after that, for permit, Insha Allah. These drawings will also be issued to potential contractors simultaneously to get quotations and start the process of selecting contractors for framing, electrical and mechanical work.

The Project Team is also awaiting final interior design concept from the Architects. These details will be finalized in September Insha Allah, and a presentation will be made to the Board for approval of interior design concept.

Other Posts

BRAVO/PROUD MOMENT

We are pleased to announce that three (3) students memorized the entire Holy Quran

Ramadan – 2018

Insha'Allah Ramadan will start either on May 17 or May 18 depending on the moon sighting

Membership deadlines for IAOS AGM 2023

For new members wanting to attend and vote in the IAOS AGM 2023, the completed membership application and membership fee…