Bi-Weekly New Mosque Update from Project Team – May 22, 2025

Alhamdulillah, the roofing work has been completed. The New Mosque now has a brand-new roof. See pictures.

The next step in the project is the placement of the heating and cooling Rooftop Units on the rooftop. The Contractor is waiting for drier ground conditions after the recent rains to bring the crane to lift the units. The units are on site (see picture) and will be placed in the next week. In sha Allah.

After approval from the IAOS Board the Project Team has placed an order for windows.

After approval from the IAOS Board has informed the chosen contractor for the stucco work.  The Project Team will sign a contract with the successful bidder soon Insha Allah

Quotations are also being floated for interior framing, with a submission date of June 6. The Project Team is also exploring potential contractors for a number of other work components.

IAOS New Mosque Project Team

Related Posts

Juma Tul Wida Prayers (جمعة الوداع)

This coming Friday is Juma Tul Wida (جمعة الوداع). There will be three Juma arrangements in the South Masjid, Inshallah. Please…

Spring Cleanup for IAOS Mosque May 13

We need Volunteers for Our Spring Clean up for South IAOS Masjid on Saturday. May 13.2023 right after Asr Salah.…

IAOS Khatam Al-Quran & Annual Fundraiser

Night of 28th Ramadan, Saturday April 6th Inshallah - Conexus Art Centre