Bi-Weekly New Mosque Update from Project Team – May 22, 2025

Alhamdulillah, the roofing work has been completed. The New Mosque now has a brand-new roof. See pictures.

The next step in the project is the placement of the heating and cooling Rooftop Units on the rooftop. The Contractor is waiting for drier ground conditions after the recent rains to bring the crane to lift the units. The units are on site (see picture) and will be placed in the next week. In sha Allah.

After approval from the IAOS Board the Project Team has placed an order for windows.

After approval from the IAOS Board has informed the chosen contractor for the stucco work.  The Project Team will sign a contract with the successful bidder soon Insha Allah

Quotations are also being floated for interior framing, with a submission date of June 6. The Project Team is also exploring potential contractors for a number of other work components.

IAOS New Mosque Project Team

Related Posts

Ramadan – 2018

Insha'Allah Ramadan will start either on May 17 or May 18 depending on the moon sighting

Important Announcement Re. Throwing Trash Around Mosque

We have received multiple complaints from a neighbor of the IAOS Masjid regarding improper disposal of trash by some volunteers.…

Fine Option/Community Services

IAOS is proud to announce that it has an approved status to provide Fine Option/Community Services Organization.