Bi-Weekly New Mosque Update from Project Team – June 19, 2025

The next step in the project is the placement of the heating and cooling Rooftop Units on the rooftop.  The units are on site (see picture) and will be placed in the next week. In sha Allah.

After approval from the IAOS Board, the Project Team has placed an order for windows. Production of Windows has started.

After approval from the IAOS Board, the Project Team has signed a contract with the successful Stucco bidder. The Contractor will commence work as per the agreed schedule soon.

Quotations have been obtained for interior framing. The Project Team will be making a recommendation for a selected contractor of interior framing to the IAOS Board, within a week, Insha Allah. The Project Team will also be making a recommendation about the dome as well as the mezzanine floor concrete to the Board very soon.

The IAOS New Mosque Project Team has also floated a tender for Electrical work, with a closing date of July 2.

 

Related Posts

Emergency Appeal – Fundraising for the People are in Crisis in East Africa

Severe drought and famine is threatening communities in some East African countries specially Nigeria, Somalia, Ethiopia, Kenya, South Sudan, and…

Important Announcement Re. Throwing Trash Around Mosque

We have received multiple complaints from a neighbor of the IAOS Masjid regarding improper disposal of trash by some volunteers.…

Ramadan 2019/1440 Calendar

Ramadan 2019/1440 Calendar to view or download.