22, May 2025
Bi-Weekly New Mosque Update from Project Team – May 22, 2025

Alhamdulillah, the roofing work has been completed. The New Mosque now has a brand-new roof. See pictures.

The next step in the project is the placement of the heating and cooling Rooftop Units on the rooftop. The Contractor is waiting for drier ground conditions after the recent rains to bring the crane to lift the units. The units are on site (see picture) and will be placed in the next week. In sha Allah.

After approval from the IAOS Board the Project Team has placed an order for windows.

After approval from the IAOS Board has informed the chosen contractor for the stucco work.  The Project Team will sign a contract with the successful bidder soon Insha Allah

Quotations are also being floated for interior framing, with a submission date of June 6. The Project Team is also exploring potential contractors for a number of other work components.

IAOS New Mosque Project Team

Related Posts

IAOS AGBM and Election 2020

The IAOS Annual General Body Meeting and Election will be held Sunday, September 27, 2020, at 2:00 PM online (an…

IAOS SUMMER SCHOOL 2018

We are Insha’Allah planning to start registration for the Summer School Program from Friday, June 1st to Saturday, June 30,…

IAOS Sunday School – 2017/2018

There are few more spots available for Sunday school program and we are accepting new students until we reach the…