Bi-Weekly New Mosque Update from Project Team – May 22, 2025

Alhamdulillah, the roofing work has been completed. The New Mosque now has a brand-new roof. See pictures.

The next step in the project is the placement of the heating and cooling Rooftop Units on the rooftop. The Contractor is waiting for drier ground conditions after the recent rains to bring the crane to lift the units. The units are on site (see picture) and will be placed in the next week. In sha Allah.

After approval from the IAOS Board the Project Team has placed an order for windows.

After approval from the IAOS Board has informed the chosen contractor for the stucco work.  The Project Team will sign a contract with the successful bidder soon Insha Allah

Quotations are also being floated for interior framing, with a submission date of June 6. The Project Team is also exploring potential contractors for a number of other work components.

IAOS New Mosque Project Team

Related Posts

IAOS Membership Fee Notice

This message is being sent on behalf of the Board to all members in good standing of the Islamic Association…

Friday Lunch Program is Back

The Friday lunch program is back effective March 15, 2019

Annual General Body Meeting & Elections 2022

The IAOS Annual General Body Meeting and Election will be held Sunday September 25th, 2022 at 2:00 PM online (online platform…