Bi-Weekly New Mosque Update from Project Team – June 19, 2025

The next step in the project is the placement of the heating and cooling Rooftop Units on the rooftop.  The units are on site (see picture) and will be placed in the next week. In sha Allah.

After approval from the IAOS Board, the Project Team has placed an order for windows. Production of Windows has started.

After approval from the IAOS Board, the Project Team has signed a contract with the successful Stucco bidder. The Contractor will commence work as per the agreed schedule soon.

Quotations have been obtained for interior framing. The Project Team will be making a recommendation for a selected contractor of interior framing to the IAOS Board, within a week, Insha Allah. The Project Team will also be making a recommendation about the dome as well as the mezzanine floor concrete to the Board very soon.

The IAOS New Mosque Project Team has also floated a tender for Electrical work, with a closing date of July 2.

 

Other Posts

IAOS New Masjid Update

The IAOS is planning to begin construction this year with your support and assistance, In Sha Allah.

IAOS Annual General Body Meeting and Election 2023

The IAOS Annual General Body Meeting and Election will be held Saturday September 30th, 2023 at 2:00 PM online (online platform…

Members Needed for Education Committee

Members needed for IAOS Education Committee It was narrated by Anas Bin Malik: The Messenger of Allah (PBUH) said, “The…