Bi-Weekly New Mosque Update from Project Team – June 19, 2025

The next step in the project is the placement of the heating and cooling Rooftop Units on the rooftop.  The units are on site (see picture) and will be placed in the next week. In sha Allah.

After approval from the IAOS Board, the Project Team has placed an order for windows. Production of Windows has started.

After approval from the IAOS Board, the Project Team has signed a contract with the successful Stucco bidder. The Contractor will commence work as per the agreed schedule soon.

Quotations have been obtained for interior framing. The Project Team will be making a recommendation for a selected contractor of interior framing to the IAOS Board, within a week, Insha Allah. The Project Team will also be making a recommendation about the dome as well as the mezzanine floor concrete to the Board very soon.

The IAOS New Mosque Project Team has also floated a tender for Electrical work, with a closing date of July 2.

 

Other Posts

IAOS AGM and Elections 2021 Results

IAOS congratulates and welcome the new members to the board. Also, IAOS thanks the members who have completed the term…

Youth Halaqa Time Change

We would like to inform you that our weekly Youth Halaqa will take place every Friday after Salat-ul-Maghrib and Family…

Qurbani with IAOS

As Eid Al Adha will soon dawn upon us insha Allah, it is important that we establish the Sunnah of…